Percentage Of Completion
Project Complete
100%
Supply
100%
Installation
100%
Civil Works
100%
Testing
100%
Project Overview
Retrofit of OHTL 66 kV (El-Shorouq-Badr) and (El-Shorouq-Elhikestep)
Short note about project
In order to build a civilized residential city, Giza Misr replaced the OHTL with underground cables which are the two circuits of El-Shorouq-El Hikestep (5 km in length) and the two circuits of El-Shorouq-Badr (3 km in length)