• Project Information
  • Company's Projects Construction of North Hurgada S/s & El-Qusair S/s overhead transmission line
  • The Owner EETC ( Owner ) L&T ( Main Contractor )
  • Project Description OHTL 220 KV

‎‎‎‎Percentage Of Completion

‎Project Complete
100%
Supply
100%
Installation
100%
Civil Works
100%
Testing
100%

Project Overview

OHTL 220 kV Safaga-Elqoseer project

Short note about project

Giza Misr was a subcontractor for L & T company in this project. The assigned part was accomplished successfully and now under tension.