• Project Information
  • Company's Projects 10th of Ramadan substation 500/220/22kv
  • The Owner EETC (Owner) XD – EGEMAC
  • Project Description Substation GIS 500/220/22KV

Project Overview

Installation and testing equipment’s of 500/220 kv substation of 10th Ramadan

Percentage Of Completion

Project Complete
90%
Supply
77%
Installation
85%
Civil Works
100%
Testing
70%
10th

Short note about project

Installation and implementation and testing equipment’s of 500 / 220 kv substation of 10Th Ramadan

XD Egymac the main contractor of 500/220 kv 10th of Ramadan invited Giza Misr to install and make testing and commissioning of this substation after finishing the civil works so we now start erection and and we expected that the work will be finished